NGUK issued an OJEU contract notice (2023/S 240-754483) on 13 December 2023, with a view to establishing a multi-year, multi-supplier framework enabling the procurement of high voltage direct current (HVDC) cable projects which include: - Design, manufacture, testing and commissioning of HVDC submarine and underground cable systems, including but not …
This DPS concerns consultancies relating to Polar Connect step 1. Polar Connect is a submarine fiber cable project with a shortest route between and East Asia starting from Norway going north of Greenland to North America and onwards to Asia. The cable is intended to be a hybrid cable that …
The scope of works to be carried out by the Supplier consists of supply of complete 525 kV HVDC cable systems and the offshore installation part of interconnector projects in connection to the Danish transmission grid. In the following, the requirements for a typical project are outlined. Deviations may, however, …